New Facility Update #10

October 2, 2009

During the weeks of September 21 and 28, brick and stone work continued on the exterior of the building.  Interior stud work was finished in the administration, rehabilitation and dietary departments. The roof was completed and flashing and gutter work will begin soon.

Sheet rocking, duct work, medical gas, fire sprinkler, electrical and plumbing rough-in work continued inside the building.  The installation of the six roof top HVAC units will take place the week of October 5th.  Window installation will also begin within the next few weeks.  Paving at the front entrance to the building will take place this week.

The project remains ahead of schedule and will be completed by September 2010.  For more information contact the Public Relations office at 728-4347.