New Facility Update #18

January 31, 2010

During the weeks of January 18 and 25, multiple subcontractors continued work inside the new hospital.  Ceiling grid installation was finished in the acute care department.  Tile installation continued in the private patient bathrooms in acute care.  Dry wall installation began in the administration department and taping began in the medical clinics and emergency department.  The ceiling grid in the acute care patient rooms was finished.

Case work for the acute care department will be delivered the first week of February.  The large windows along the south end of the main corridor as well as the windows near the chapel and in the dining room were delivered and will be installed soon.  The lifts in the acute care department are being installed in the patient rooms.

The project is still on schedule for completion this fall.  For more information contact the Public Relations office at 728-4347.